Wastewater Lift Station 19 Rehabilitation Project; Laguna Madre Water District

400 Padre Blvd, South Padre Island, TX 78597

Wastewater Lift Station 19 Rehabilitation Project; Laguna Madre Water District

      • Completion Date: 2014
      • Location: South Padre Island TX
      • Texas Owner: Laguna Madre Water District
      • Engineer: LNV Engineering
      • Description: The project consists of the installation of a new, 15.5′ diameter fiberglass wet well, concrete valve vault and wet well slab, discharge piping and valves, electrical enclosure, wiring, 300KW stand-by generator, telecommunication system and new wooden perimeter fencing. Work included the conversion of an existing, in-service concrete wet well to a receiving manhole and the relocation of existing lift station pumps and controls to the new fiberglass wet well. Additionally, the project consisted of the demolition of an abandoned lift station and the relocation of on-site utilities and existing odor control system.